Compact single-housing design
Battery, inverter stack, and EMS controller integrated in one cabinet footprint. No separate inverter enclosure to cable, permit, or cool. Cabinet weight under 20.0 t.
PRODUCTS / BESS
C&I BESS cabinet
Plug-and-play installation
Below, you will find the detailed technical specifications for the Battery Energy Storage System (BESS) EOM I 1300.
Product rationale
Four design decisions that matter when you’re specifying a mid-size industrial BESS, not marketing prose.
Battery, inverter stack, and EMS controller integrated in one cabinet footprint. No separate inverter enclosure to cable, permit, or cool. Cabinet weight under 20.0 t.
Shipped pre-configured, factory-tested, and ready for grid tie-in. Easy to relocate if the site plan changes. Typical on-site commissioning window: 1-3 weeks once delivered.
Sits alongside the cabinet for flexibility stacks multiple units in parallel, interfaces with site SCADA via Modbus-RTU/TCP, and runs the full Monbat Energy EMS app suite (Peak Shaving, Self-Consumption, Grid-Supportive Charging, Market Participation).
IP55 battery cabinet protection, –20 °C to +50 °C operating range, integrated fire safety system, and liquid-cooled LFP chemistry specified for the cycling profiles of peak shaving, backup, and trading workloads.
A real EOM I 1300 deployment.
Charge Point Operator
CHALLENGE
The charging site requires 600 kW to support current and future demands. The existing grid connection is limited. Expanding the grid connection would require significant infrastructure updates with estimated cost of €267k.
SOLUTION
MONBAT Energy EOM 780 enables DC fast charging with the EMS configured to Peak Shaving, Dynamic Tariffs and Dynamic Load Balancing for charging stations. Three weeks from installation to live operation.
RESULTS
A major achievement driven by outstanding teamwork, decisive project management and relentless focus. From planning to
commissioning, the entire project was delivered in only six months bringing value to the business faster than expected.
See if these numbers are realistic for your facility
Further questions? Let’s personalize the information to your case.
It carries 1305 kWh nominal / 1250 kWh usable at beginning of life, with 500 kW rated AC power – battery, power conversion, and EMS all inside a single 6,096 x 2,600 x 2,591 mm housing under 20 tonnes. That envelope suits mid-to-larger C&I sites: manufacturing peak shaving, multi-bay fast charging, or stacked self-consumption and trading. The honest answer is that “right size” is a function of your load profile, not nameplate – send us interval meter data and we’ll size it against your actual demand curve.
Yes. The system is modular by design you parallel additional EOM I 1300 cabinets and the EMS coordinates them as one logical system, so peak shaving, backup, and trading logic apply across the whole installation rather than per cabinet. This is also how you scale later: start with what today’s load needs and add cabinets as the site grows, without re-engineering the EMS layer or replacing the first install.
The power conversion stage complies with VDE-AR-N 4105:2018 (low-voltage) and VDE-AR-N 4110:2018 (medium-voltage), operating at 315–450 Vac three-phase, 50/60 Hz, with current THD below 3% at rated power and a continuously adjustable power factor from 0.9 inductive to 0.9 capacitive. The full certification stack – UN 38.3, IEC 62619, UL 1973, UL 9540A, IEC 62477-1 LVD and IEC 61000-6-2/4 EMC on the battery side, plus IEC 62477 and IEC 61000-6-2/-6-4 on the PCS side – is what financing partners and insurers look for, and it’s recognised without additional due diligence.
Delivery for a standard EOM I 1300 configuration is typically 8-12 weeks. On-site installation runs 1-3 weeks for a typical C&I facility; because the cabinet ships pre-assembled and factory-tested as a single plug-and-play unit, the disruptive part – grid tie-in and is usually a single shift scheduled outside production hours. The unit arrives at 30% state of charge and is commissioned on site. We coordinate with your facility manager and local DSO from day one.
No, the PV connection is optional. When you want it, the EOM I 1300 accepts up to 500 kW of solar directly (up to five 30 kW DC/DC modules, 800 Vdc, one MPPT per module). Because the panels connect to the battery DC bus inside the same housing rather than through a separate AC inverter, you get higher round-trip efficiency on self-consumed solar (system round-trip efficiency is ≥ 88%). You can specify it now or add modules later; if your site has no PV and no plans for it, you simply leave the inlet unpopulated and lose nothing.
possible pairing
Hardware is only half the system. The EMS is what decides in real time, against your tariff and your load profile when to charge, when to discharge, when to hold, and which apps to prioritise.
The same controller runs Peak Shaving, Self-Consumption Optimisation, Grid-Supportive Charging, Backup, and Market Participation and the mix can be reconfigured as your commercial strategy evolves, without hardware changes.
The EOM I 1300 is one of seven cabinets and containers.
260 kWh cabinet. Mid-size industrial and commercial sites.
1045 kWh cabinet. Large Industrial and commercial sites.
1560 kWh cabinet. Large industrial and commercial sites.
Book a 30-minute call with a Monbat Energy engineer. We’ll review your load profile, peak demand, grid connection, and critical-load map and tell you honestly whether the EOM I 1300 is the right cabinet, or whether you need a different model in the range.